speaking at an administrative council meeting of the Bushehr Province Ports and Maritime Department attended by the PMO Managing Director, Abdolsaeed Abbasi stated that numerous projects in infrastructure development, equipment procurement, and port upgrading have been carried out across the province in recent months, with commissioned projects totaling approximately 2.32 trillion rials in value.
Noting that the Genaveh Port development project has reached 95 percent progress, he added that the project is expected to be completed and put into operation by the end of the current year
Abbasi described completing the infrastructure of the Negin Port Complex as one of the province’s major development priorities, stating that given the presence of major investors at the complex and the PMO’s commitments to provide basic infrastructure—including water, electricity, and road access—completing the power supply project holds particular importance.
Pointing out that the road infrastructure of the Negin Port Complex became fully operational last year, he noted that under current conditions, the complex’s most pressing requirement is completing the electricity supply network, which plays a decisive role in accelerating investor attraction and operations. Given the high share of equipment and materials in the project’s execution costs and rising prices, any delay could drive up completion expenses; accordingly, support and the allocation of necessary funding to expedite its implementation are essential.
Referring also to development projects at Morvarid Port on Kharg Island, Abbasi stated that the construction of a Ro-Ro berth at the port is underway with a budget of 1.8 trillion rials, and despite the island’s specific conditions and the challenges of operating during wartime, the necessary follow-ups are being pursued to procure required equipment and advance the work. The project currently stands at 5 percent physical progress.
He also announced plans to execute new civil and equipment projects at the province’s ports, adding that projects with a budget of around 22 trillion rials have been earmarked for equipment procurement, alongside initiatives valued at approximately 260 trillion rials for developing and maintaining existing infrastructure and facilities.
Turning to the berth-side dredging project at Bushehr Port, the Director General of the Bushehr Province Ports and Maritime Department said the project is currently underway at roughly 70 percent physical progress and requires an additional 3.95 trillion rials in funding for completion, accounting for cost adjustments and price increases.
In conclusion, he emphasized the need to support and secure the required funding for infrastructure and maintenance projects across the province’s ports, expressing hope that by accelerating financial allocations, ongoing projects will be completed and commissioned according to schedule.